Manville Road Corridor Improvement Project – Update

Work on the south side of Manville Road between Wheeler Avenue and Tompkins Avenue is near completion. Following this work, the project will move to the southeast corner of Tompkins Avenue to replace the pedestrian ramp, curb and sidewalk.

In early November, work will shift to the segment of sidewalk between Vanderbilt Avenue and Grant Street on the north side of Manville Road. This will include:

· Replacement of a fire hydrant

· Sidewalk demolition

· Installation of new sidewalk

· Layout and pouring of new curbs

There may be some impacts to traffic in the area as work occurs. The schedule is weather dependent and subject to change. Further updates will be provided.  

Due to long lead-times with traffic signal equipment, work at the Manville/Memorial/Grant Street intersection is scheduled for early 2023. This includes the construction of the right-hand turn lane at Memorial Plaza and the removal of the slip lane. For an overview of the project, please visit: https://www.pleasantville-ny.gov/projects-initiatives/pages/manville-rd-...