Con Ed Gas Main Replacement Project on Marble Avenue Starting the Week of April 9th

Project Location:  Con Ed will be moving forward with a gas main replacement project on Marble Avenue from the Saw Mill Exit 27 access road to Pine Street; and, a second portion on Marble Avenue from Hobby Street through the Bedford Road intersection, stopping in front of Key Foods on Pleasantville Road.

Project Schedule:  Con Ed is planning to start the project the week of April 9 with a 6 day-a-week construction schedule from 7AM to 7PM. The entire project is expected to be completed in 3 months. During this time there may be single lane closures. The Village has required that two lanes remain open during morning and evening rush hours.